Golden Hills Solar Milestones

May 26, 2011              
Geologic and Geotechnical Review Completed

February 22, 2012      
California Department of Fish and Game Review Completed

November 5, 2012     
CEQA study completed and approved with a mitigated negative declaration

November 9, 2012
Biological Resource Assessment Completed

April 19, 2013              
Conditional Use Permit Issued by Stanislaus County

April 29, 2015
LGIA Application Filed with CAISO

June 16, 2015                          
CAISO Filing Approved with Queue Number 1118


January 2016
Phase 1 CAISO  Interconnect Study complete

 
Targeted Milestones (to align with current tax incentives)

Spring 2016
Construction begins on Phase 1